The Big Lift Improvement

The programme will see lift and escalator facilities renewed or upgraded up to the end of 2024

At Iarnród Éireann we are investing in our stations with The Big Lift upgrade. Over the next year we're making some big changes by replacing and upgrading our lifts.

The Big Lift means big improvements for people with mobility issues. There may be some disruptions now, but this work will provide extra reliable station access for everyone in the future.

Nineteen stations across the network will see lift replacements or upgrades completed in 2024. In total, 52 stations across the rail network will see major investment between 2020 and 2024.

While we are upgrading, alternative arrangements will be advised for customers of reduced mobility to ensure continued access at stations.

c3ebbd63-5bce-4f71-b8ce-bd8526a40921.jpg

2024 Big Lift dates, locations and accessibility details for each station are listed below:

StationWork beginWork Finish
Dunboyne06/08/202402/09/2024
Hazelhatch (Platform 1)07/08/202406/09/2024
Rush & Lusk12/08/202406/09/2024
Kent Station, Cork12/08/202425/09/2024
M3 Parkway26/08/202427/09/2024
Hazelhatch & Celbridge (Platform 5 / Island)02/09/202427/09/2024
Donabate02/09/202427/09/2024
Hansfield16/09/202411/10/2024
Parkwest & Cherry Orchard (Platform 5 / platform 1)23/09/202418/10/2024
Tara Street23/09/202418/10/2024
Bayside30/09/202425/10/2024
Parkwest & Cherry Orchard (Island)14/10/202408/11/2024
Newbridge14/10/202408/11/2024
Raheny21/10/202415/11/2024
Clondalkin & Fonthill29/10/202423/11/2024
Navan Road Parkway27/11/202420/12/2024
Adamstown18/11/202420/12/2024
Clongriffin25/11/202420/12/2024
Clonsilla29/10/202423/11/2024
Malahide22/07/202416/08/2024
Rush and Lusk12/08/202406/09/2024